Airport Perimeter Fence Project

Date of Award:
May 20, 2019
Contractor:
Custom Fence
Amount:
$662,673.90

Funding Source(s) :

  • Federal Aviation Administration Airport Improvement Program Grant Funds
  • City of Fallon Airport Fund

Completion Date:

The Airport Perimeter Fence Project, AIP No. 3-32-0008-021-2019, PWP-CH-2019-150, consisted of the removal of approximately 19,225 linear feet of existing 4-foot wire fence, clearing and grubbing the fence line, installation of approximately 19,310 linear feet of 6-foot chain link fence with 3 strand barb wire, and the installation of 2 cantilevered gates with operators and key pads. This project was funded at 93.75% by Federal Aviation Administration Airport Improvement Program grant funds and 6.25% by the City of Fallon Airport Fund.